1. Introduction

Peak Load Management is designed to help users monitor and control power consumption within a microgrid. Its primary goal is to prevent power peaks from exceeding a defined threshold (Setpoint), thereby avoiding high demand charges or grid overloads. By integrating Battery Energy Storage, the system can automatically discharge power when a peak is imminent, achieving "peak shaving."

Peak Load Management is activated if "Activate Load Managent" toggle is activated in the "Project Settings" based on entered "Setpoints", "Upper Threshold" and "Lower Threshold". alt text

Users inactivate "Activete Load Managent" toggle, "Turn off" symbol displays to present the "Peak Load Management" feature of the system is currently inactivated. alt text

2. Interface Navigation & Layout

This module contains three main tabs:

Overview: Displays real-time power status, forecasts, and system active control states.

Configuration Settings: Used to display predefined limits, limits based on constraints, and different actions to avoid peak load.

Priority List: Used to display the priority of various Charging Infrastructure(WALM) when peak load shedding is required.

3. Overview page

The Overview page is divided into four main areas: Key Metrics Cards, Real-time Trend Chart, Legend, and Active Controls List.

3.1 Key Metrics Cards

The five cards at the top of the page provide core operational data for the current system status:

Name Description
Grid Power The actual power currently drawn from the grid.
Remaining Headroom The available power remaining before reaching the peak Setpoint.
15-Minute Grid Power Forecast The system's predicted average grid power for the next 15 minutes, used for proactive decision-making.
Control Stage The current control stage the system is in.
SoC Battery Storages The average State of Charge (SoC) percentage of all connected controllable battery storages.

Vertical status indicator bars Indicators:

Grid Power

Name Description
Red Over Setpoint
Yellow Over Upper Threshold
Green Under Upper Threshold

Remaining Headroom

15-Minutes Grid Power Forecast

Name Description
Red Over Setpoint
Yellow Over Upper Threshold
Green Under Upper Threshold

Control Stage - Stage [number according to actual stage]

Name Description
Grey Not active
Green Active
Red Last stage reached and Peak Load not avoided ( Notification of the User )

Battery Storage SoC

Name Description
Grey there is no battery storage
Yellow SoC > 80%
Red SoC < 20% or SoC = 0%

alt text

3.2 Real-time Trend Chart

The chart displays the trends of power parameters over time: alt text

Tooltip: Users can hover over the chart displays data for a specific point in time.

3.3 Legend

The checkboxes on the right side of the chart control the visibility of different data curves. A checkmark indicates the item is currently displayed. Users can select/unselect checkboxes. alt text

If "Turn off" symbol displays, "Setpoint", "Upper/Lower Threshold" curves and checkboxes will disappear automatically. alt text

3.4 Active Controls List

This section shows the current control status of individual component which on stages.(Configuration Settings - Actions to Avoid Peak Load)

Active Controls: Lists managed components which from stages.

Status: Displays the current action state of the component.(Unchanged/Increased/Decreased)

Active Power: The actual current power of the Component.

Intervention: The power adjustment requested by the system for peak shaving. alt text

4. Configuration Settings page

This page is divided into two main areas: Limits for Peak Load Detection and Actions to Avoid Peak Load.

4.1 Limits for Peak Load Detection

Predefined Limits:

The values are from Project Settings - General - Load Management settings. Click the gear icon ⚙️ Limits, it navigates to Project settings page, and you can set values for Setpoint, Upper Threshold, Lower Threshold here. alt text alt text

Limits Based On Constraints:

If not configured, it displays as -kw. alt text

If configured, the values are from Enabled Grid Setpoint Change constraint. Click the gear icon ⚙️ Constraints, it navigates to Constraints & Tasks page, and users can add new Constraints and Tasks here. alt text

Users can add a new Grid Setpoint Change constraint.

Steps:

  1. Click "Add" button.
  2. Select "Grid Setpoint Change" Constraint Type and enter suitable values.
  3. Click "Add" button and a new constraint is created successfully. alt text alt text alt text alt text

During Grid Setpoint Change type constraint enabled period, System's Setpoint, Upper Threshold, Lower Threshold of Predefined Limits are overwrited temporary by Limits Based on Constraints. alt text alt text

Note: Grid Setpoint Change type Constraint needs to wait to next 15-Minute Time Frame.

4.2 Action to Avoid Peak Load

When the system meets the trigger condition, the system will execute actions defined here in the order of "Stages."

Stage configuration

•Add a new Stage 1 - Discharge all at once for Battery Storages

  1. Click the green + Add Stage button

  2. Select "Discharge Battery Storages" for "Action" field

  3. Select "Dischage all at once" for "Discharge selection" field

  4. Enter suitable value for "Reduce to Target SoC"

  5. Select target battery storage for "Component" field

  6. Click "Save" button, and Stage 1 is created successfully. alt text alt text alt text

Notes:

  1. If the battery storage's SoC is "Not Set", "Some components have no Minimum SoC. Please change in component settings." message is displayed, users can click "Edit" button to set it. alt text alt text

Step 1: Click "Edit" button, there will open a new window, and navigate to "Microgrid Components - Components- Control Parameters" page.

Step 2: Click "Edit" button, enter suitable value for "Minimum State of Charge" field, click "Save" button. alt text alt text alt text Step 3: Switch to the first window, the setted value is populated. alt text

  1. If value of "Target SoC/Minimum SoC" is higher than value of "Reduce to Target SoC", "Minimum SoC of some components is higher than Target SoC. " message will display, users can still add the battery storage to the stage. alt text

  2. If want to add more Components on this stage, users can click "Add Component" button.

  3. If want to delete added Component, users can click "Trash" button.

•Add a new Stage 2 - Discharge one after each other for Battery Storages.

  1. Click the green + Add Stage button.

  2. Select "Discharge Battery Storages" for "Action" field.

  3. Select "Dischage one after each other" for "Discharge selection" field.

  4. Select target battery storage for "Component" field.

  5. Click "Save" button and Stage 2 is created successfully. alt text alt text alt text

•Add a new Stage 3 - Decrease Consumption of Controllable Consumers

  1. Click the green + Add Stage button

  2. Turn on the toggles that users want.

  3. Click "Save" button and Stage 3 is created successfully. alt text alt text alt text

•Add a new Stage 4 - Turn Off Binary Controlled Consumer

  1. Click the green + Add Stage button

  2. Select "Turn off Binary Controlled Consumer" for "Action" field

  3. Select target component for dropdown list for "Component" field

  4. Click "Save" button, and Stage 4 is created Successfully. alt text alt text alt text

Note:

Before performing the turn-off Binary Controlled Consumer stage operation, please confirm that the status indicator next to the target component is green. Green indicates the component is online, and the system can successfully issue the 'Turn Off' command. If the indicator is red, it means the component is offline, and the system will not be able to effectively control it to reduce power consumption. alt text

•Edit a Stage

  1. Click "Edit" button.

  2. Selected target values.

  3. Click "Sava" button.

•Delete a Stage

  1. Click "Delete" button.

  2. Click "Delete Anyway" button.

•Notification of the User stage

This stage is default notification stage, this stage is entered when automatic control methods have been exhausted but the overload problem persists. alt text alt text

Tips:

  1. If users want to adjust the sequence of stages,users can do it by dragging. Move the mouse to the Drag Icon (≡), and the cursor will change to cross. hold on the left mouse button and drag the stage to the desired location.

  2. Click "Show All ↓" button will expand the list downward to expand all the component assigned to that stage.

  3. Click "Hide ↑" to hide the extra items to save screen space.

Explanation of Stage

Discharge Battery Storages

Name Description
Target The desired state of charge (SoC) the battery storage is intended to discharge down to.
Actual Real-time state of charge(SOC)
Blocked The battery storage can not be used because license capacity exceeded

Descrease Consumption of controllable Consumers

Name Description
Low Priority Classification for Components that are minimal.
Mid Priority Classification for Components that are important, but not critical.
High Priority Classification for Components that are critical.
Limit Refers to the maximum power consumption limit allowed for the component during this stage.
Previous Refers to the power limit value of the component before entering this stage.

5. Priority List page

In the "Priority List" tab, users can view and manage the priority order of all controlled Charging Infrastructure(WALM). When executing peak-shaving actions, the system will limit WALM power consumption sequentially based on the order in this list. alt text Tips:

  1. Users can click and hold the icon to drag rows up and down to the desired position. alt text
  2. Users can click and hold the Priority line to change the priority quickly. alt text